On October 7, 2023, JSC "Alatau Zharyk Companiyasy" put into operation the substation PS-110/10kV "Kokozek".
The project implemented by JSC "Alatau Zharyk Companiyasy" will provide electricity to the industrial zone in the Karasai district.
The launched new substation will allow implementing new projects, as well as upgrading existing projects. In addition, it will attract investment in the industrial zone of the Karasai district.
The substation will provide reliable and stable power supply to 346 small and medium-sized businesses, 1362 consumers of the housing sector of the Karasai district.
The construction of the substation PS-110/10kV "Kokozek" was carried out at the expense of JSC "Alatau Zharyk Companiyasy", a company in the structure of the electric power holding JSC "Samruk-Energo".