On the territory of the West Kazakhstan region, 11 facts of erosion (1 – republican, 1 – regional and 9 – local significance) of the roadway were registered in 4 districts of the region (Chingirlau 7 of local significance, Karatobinsky – 1 of regional significance and 1 of local significance, Burlinsky – 1 of republican significance and Bayterek district – 1 of local significance).
For reference: To date , 104 km. the bypass road "Podstepnoye – Fedorovka – gr.RF" is being worked on.
There is a bypass road on 102 km of the Zhympity-Karatobe regional road, there is access to passenger cars. Restoration work will be completed on 12.04.2023. Funds are provided for the construction of additional pipelines.
At 38 km . Karatobe-Karakol provides funds for the construction of additional pipelines Temporary restoration works have been carried out on the 60th kilometer of the Chingirlau-Ardak-Aktau highway, after the allocation of additional funds from the regional budget, a concrete slab of the surface of the laid soil will be additionally laid.
At 39 and 52 kilometers of the Chingirlau-Akshat-Segizsai highway, at 9 km. Chingirlau - Almazny temporary restoration works have been carried out, after the allocation of additional funds from the regional budget, culverts will be installed.
There is a bypass road along 108 and 107 km of the Chingirlau-Akshat-Segizsai highway, after the allocation of additional funds from the regional budget, restoration work will be carried out.
Between the villages of Aschysai and Myrzagara (2 km between the villages). There is another bypass road. after the allocation of additional funds from the regional budget, restoration work will be carried out.
At 28 km. highways Peremetnoe – Shalgai (district - Bayterek) there is a bypass road. after the allocation of additional funds from the regional budget, restoration work will be carried out.