At the stage of completion, projects for the construction of roads in the mkrn Construction-4 s. Have Kyzyltu and roads on 14 streets in the southern part of Aksai. Mayor of Burlinsky district mirzhan Satkanov visited the facilities today, listened to the report of the head of the contract organization "Aksaybusinessstroy" LLP Anvar Agayev on the spot, and answered questions from residents.
The first project was implemented as part of the state program"employment Roadmap". The length of paved roads was 5.5 km. The project includes ditches, sidewalks and culverts.
As part of a separate project, 55 lights were installed in the mcrn Construction-4.
The project of road construction in the southern part of Aksai was implemented within the framework of the state program "development of regions". It was designed for 2 years-2019-2020. The roadbed with asphalt surface is almost 10 km long. The project also includes ditches, sidewalks, culverts and access roads to courtyards.
The contractor has strengthened the bypass dam in this part of the city at its own expense (outside the project).