Report on the implementation of the Territorial Development Program of Inder district for 2021-2025

 

Methodology for monitoring the Strategic Development Plan of the Republic of Kazakhstan, state and government programs, strategic plans of government agencies and territorial development programs

Appendix 2

Object

Report on the implementation of the Territorial Development Program of Inder district for 2021-2025

Reporting period ____2021__________

Approved by the decision of the district maslikhat №-6-VІІ of  January 15, 2021

State body Inder district department of economy and finance

  1. Information on the implementation of the program

№

Name

Unit of measurement

Source of information

Responsible executors

Execution

Source of funding

Budget program code

Execution information

Basic (initial) value

plan

fact

1

2

3

4

5

6

7

8

9

10

11

І. Regional economic growth

1.Goal: Priority development of non-resource industries

1.

Investments in fixed assets in the manufacturing industry

mil. tenge

Statistical information

VCT

10

10

553,3

OS

*

According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars 

Completed

Events

1

Attracting investments in fixed assets with" TҰЗ" LLP for the production of table salt and the implementation of a plant for the production of technical salt

mil. tenge

Information from «ТҰЗ» LLP

VCT

5

5

0

OS

*

The project to open a plant for the production of table salt has been postponed to 2022. The reason is that due to the quarantine situation, the necessary equipment from foreign countries was not received on time.

2

Attracting investments in fixed assets for the implementation of a plant for the production of dry building mixes with «ИСИГипсИндер» LLP

mil. tenge

Information from

«ИСИГипсИндер» LLP

VCT

5

5

317,5

OS

 

In the reporting year «ИСИГипсИндер» LLP invested млн 317.5 million in the implementation of the plant for the production of dry building mixes. investments in the amount of tenge were attracted, new jobs were created, 4 people were employed.

3

Attracting investments for the production of dry building mixes, building gypsum with «ИСИГипсИндер»  LLP

mil. tenge

Information from

«ИСИГипсИндер» LLP

VCT

 

 

235,8

OS

 

In the reporting year, «ИСИГипсИндер» LLP invested млн 235.8 million in the production of dry building mixes and building gypsum.investments in the amount of tenge are attracted.

2  Goal: Improving the competitiveness of agro-industrial sectors

2

Index of physical volume of gross agricultural output

%

Official statistics

Agriculture

102,7

102,7

104,1

*

*

The volume of gross agricultural output in the reporting year amounted to 11 Millard 512 million Tenge, the physical volume index is 104.1%.

Completed

3

The share of increasing the volume of crops, including increasing the share of drip irrigation methods

%

LB

departmental report

Agriculture

49

49

49

*

*

In 2020, 11 farms were engaged in drip irrigation with a total area of 1545 hectares, of which 471 hectares. In 2021, 1,590 hectares were allocated for the entire crop, of which 779 hectares, or 49%, were irrigated by drip method by 17 farms.

Completed

Events

1

Development of a fund for increasing the area under forage crops to 490 hectares for animal husbandry

Ga

LB

departmental report

Agriculture

440

440

500

*

*

For animal husbandry,the area under which forage crops are sown is 500 hectares

2

Purchase of 47 new agricultural machinery and equipment in order to update the agricultural machinery fleet

unit

LEB

departmental report

Agriculture

12

12

12

*

*

In the reporting year, 13 units of agricultural machinery and equipment (tractors and aggregates)were purchase. These are" Dastan " - 1," ER Tostik "- 1, peasant farm"Asyl Agro "-2, individual entrepreneurs"Esmagambetov "-2,"Zhalgasbayev "-2,"Uteshov "-2,multi-specialty agricultural college Inder-1, LLP" Kaztatservice " - 1.

 

 

 

3

Purchase of drip irrigation equipment by economic entities

unit

LEB

departmental report

Agriculture

12

12

21

 

 

In the reporting year, 17 farms purchased drip irrigation equipment, and 4 farms purchased sprinkler irrigation equipment.

mil. tenge

1,1

1,1

1,2

OS

 

THE SECOND DIRECTION: Ensuring a new quality of life

3. Goal: Ensuring employment and creating new jobs

4

Number of jobs created, including

unit

LEB

report

ODIHR

1271

1271

1758

 

*

By the end of 2021, 1,758 new jobs were created in the district (including 869 permanent and 889 temporary). "In particular, within the framework of the state programs" "employment roadmap for 2020-2021" "45 people, within the framework of the housing construction program" "Nurly zher ""- 99 places, within the framework of the program ""Enbek ""- 805 places, under the program ""Auyl El besigi "" - 22 places, employers of the district - 581 places, since the beginning of the year 206 new entrepreneurs have been registered in the tax administration."

Completed

permanent

551

551

869

 

temporary

720

720

889

 

5

Share of employed recipients of able-bodied TSA (conditional monetary assistance) and those involved in active employment promotion measures (in the total number of able-bodied recipients of the TSA)

%

LEB

report

ODIHR

69,0

69,0

69,0

 

 

In the district, from January 1 to December 31, 2021, the number of recipients of social assistance (conditional monetary assistance) was 542 people, including 374 able-bodied people, the share of able-bodied people among recipients of targeted social assistance was 69.0%.

Completed

The event

1

«ИСИГипсИндер»  LLP  and" Inder TUZ COMPANY " LLP create new jobs by expanding their currently operating factories to provide employment for unemployed citizens on the ground

*

VCT

ODIHR

*

*

*

*

*

«ИСИГипсИндер»   LLP has completed the expansion of the plant, created new jobs and employed 5 people. Due to the incomplete expansion of the existing plant of INDER TUZ COMPANY LLP, no new jobs were created

 

2

Attracting local unemployed citizens to short-term training courses in specialties necessary for plant expansion projects

*

ODIHR Department

statistical reports 1T and 2T

ODIHR

 

*

*

*

*

*

Since the beginning of the year, 57 people from among the unemployed registered in the District Employment Center have been sent to short-term courses.

3

Placement of unemployed citizens for new jobs at the facilities under construction through the implementation of a project for the construction of schools, kindergartens and sports complexes in rural areas

*

ODIHR

Department information

ODIHR,

akims of settlements and rural districts

*

*

*

*

*

In 2021, under the program" Auyl-El besigi", 22 people were sent to 3 projects in the District ( major repairs of street lighting in Yntymak village, construction of a sports and Recreation Complex in Koktogay village, construction of a sports and Recreation Complex in Zharsuat village), 47 people were employed in 1 project under the program" Employment roadmap " (construction of a secondary school named after K. Eskaliyev in Esbol village). In total, in 2021, 4 projects were implemented, and 69 unemployed citizens of the district were employed in the created jobs.

4

Holding job fairs with employers

*

ODIHR

reporting of the Department

ODIHR,

akims of settlements and rural districts

 

 

 

*

 

 

*

 

 

*

 

*

 

*

In 2021, 4 job fairs were held in the district, 181 of the 342 people who took part in the Fair were provided with permanent jobs

5

Public Works

million

tenge

ODIHR

reporting of the Department

ODIHR,

akims of settlements and rural districts

112,0

123,2

123,2

 

 

Since the beginning of the year, it is planned to send 560 people to paid public works, by the end of the year, 40 people have been allocated additional funds at the expense of the local budget in the amount of 5.3 million tenge, and 600 people have been sent to work. At the end of the term, 248 people were employed on a permanent basis. For 2021, 112.0 million tenge was approved for this program, and during the year it increased by 123.2 million tenge.

22,0

 

43,2

 

43,2

RB

 

801004011

 

90,0

80,0

80,0

LB

 

 

801004100

6.

Youth practice

million

tenge

ODIHR

reporting of the Department

ODIHR

 

30,6

20,1

20,1

RB

 

801004011

 

According to the program" youth practice", 70 young professionals were sent to institutions of the district for a 6-month internship, as a result of which 47 young people were provided with permanent jobs. For 2021, 30.6 million tenge was allocated for this program. at the end of the year, funds in the amount of KZT 10.5 million were approved. the funds in the amount of KZT 20.1 million were transferred to the state grant and updated. the tenge is fully disbursed.

7

Social work

million

tenge

ODIHR

reporting of the Department

ODIHR,

akims of settlements and rural districts

22,9

21,8

21,8

RB

 

801004011

 

In 2021, it is planned to employ 90 people in social jobs, and 100 people took part in the program. As a result, 78 people are provided with permanent jobs. For 2021, funds in the amount of 22.9 million tenge were approved for this program, and 21.8 million tenge was specified

4. goal. Ensuring the quality of services of general secondary education and pre-school education

6

Reduction of the number of emergency and three-way schools, including

unit

Conclusion of the National Center of «Құрылыс консалтинг» JSC

ABB, JSCB

1/0

1/0

1/0

*

*

K. Eskaliyev in esbol village secondary school named after In 2017, it was recognized as an emergency school. Currently, construction of a school for 320 children is underway in Esbol village. The contractor is "Ondasyn Stroy" LLP. There is no three-shift school

Completed

Emergency

Three-shift

 

7

Share of schools that have created conditions for Inclusive Education

%

LEB

report

ABB

80,0

80,0

 

*

*

The number of children with disabilities enrolled in general education schools determined by the medical, pedagogical and psychological expert commission for health reasons in the district is 154. of these, 146 children with special educational needs are covered in 12 out of 15 schools. On April 23, 2021, the Regional Department of Education sent 2 Budget applications for the necessary equipment for creating inclusive conditions in schools. However, no funds were allocated. Therefore, the indicator is not implemented according to the plan.

Failed

The event

1

Construction of a school for 320 children in Esbol village, Inder distric

million tenge

Acceptance certificate

ABB, JSCB

1 145,8

1 145,8

233,2

LB

271086

According to the results of 2021, 233 million 228 thousand 160 tenge was disbursed.

2

The presence of raised (tactile) stripes on the stairs

million tenge

acceptance certificate

ABB

0,300

0,300

0

LB

261067

The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated

3

Sink and toilet equipment for children with musculoskeletal disorders and visual impairments

million tenge

acceptance certificate

ABB

0,5

0,5

0

LB

261082

The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated

4

Functional desks, tables for children with cerebral palsy

million tenge

acceptance certificate

ABB

1,0

1,0

0

LB

261082

The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated

5

Lamps for children with visual impairments

million tenge

acceptance certificate

ABB

0,3

0,3

0

LB

261067

The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated

6

Organization of subject Olympiads, creative art competitions for children with disabilities

*

LEB

departmental report

ABB

*

*

*

*

*

 

5. goal: to increase the availability of social infrastructure facilities for citizens

8

Provision of sports infrastructure per 1000 people

%

Stat information and

AMTDDShSB

AMTDDShSB

21,3

21,3

21,3

*

*

In the District, 3 sports complexes, a wrestling hall, a Sports Hall of 16 educational organizations, 1 shooting range and a Sports Hall of a multidisciplinary Agricultural College serve the population. The total area is 6676.9 square meters. Sports infrastructure is provided by 21.3% per 1000 people of the population.

Completed

The event

1

Construction of a sports complex in the village of Zharsuat

million tenge

*

DShSB

228,0

228,0

203,0

RB

467079028

In 2021, 203.0 tenge was allocated from the Republican budget for the work of the zharsuat Sports Complex. The work of the Sports Complex is completed by 90%. It is expected to be commissioned by the first quarter of 2022

2

Construction of a sports complex in Koktogay village

million tenge

 

*

JSCB

200,0

200,0

170,7

RB

467079032

Construction of Sports Complex in koktogay village continue

3

Purchase of a sports complex building in Orlik village

million tenge

 

*

JSCB

195,0

195,0

195,0

LB

467008015

The building of the Sports Complex in the village of Orlik was transferred to the balance sheet of the Department of Physical Culture and sports of Atyrau region

4

Construction of a sports field in the KSU "secondary school named after sh.Ualikhanov" in the village of inderbo

million tenge

 

*

JSCB

35,9

35,9

35,9

LB

467008028

In 2021, the sports ground of the secondary school named after sh. Ualikhanov was put into operation..

5

Construction of a sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor

million tenge

 

*

JSCB

15,3

15,3

15,3

LB

467008028

A sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor has been adopted

6

Construction of a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor

million tenge

 

*

JSCB

200,0

200,0

11,4

RB

467079032

The construction of a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor has been completed and put into operation. The balance was transferred to the school

100

LB

467008028

7

 

Construction of a sports field in KSU "Koktem Kazakh Secondary School" in the village of inderbor

million tenge

 

*

JSCB

123,8

123,8

-

LB

467008015

Budget applications were sent to the Construction Department of Atyrau region. Construction will begin at the time when the funds are provided

8

Construction of a sports field in the KSU "secondary school named after M. Auezov" in the village of inderbor

million tenge

 

*

JSCB

154,0

154,0

 

LB

467008015

Budget applications were sent to the Construction Department of Atyrau region. Construction will begin at the time when the funds are provided.

Third direction: a comfortable and safe area for living

7. goal: to increase the pace of housing construction to ensure housing affordability for citizens

10

Provision of Housing per inhabitant

sq.m per person

Official statistics

ODIHR

22,2

22,2

22,2

*

*

According to the results of 2020, the total housing stock was 669,735.5 sq. m., and in January –December 2021, 462 apartments with an additional area of 53,338 sq. m. were put into operation. The total housing stock in the reporting year was 723,073.5 sq. m.and 22.2 sq.m. per person.. (population – 32545)

Completed.

11

Share of reducing the number of Emergency Multi-storey residential buildings

*

LEB

departmental report

ODIHR

25,3

25,3

29,6

*

*

The number of multi – row residential buildings in the district is 64, of which the number of dilapidated housing is 19, or 29.6%. Due to the fact that the housing commissioned in the reporting year is planned to be transferred to the categories of large families and low-income families, it is not possible to move the housing recognized as dilapidated. No funds were allocated for the construction or purchase of housing in this category. Not done.

The event

1

Construction of a 48-apartment 4-storey residential building No. 1 On Site No. 11 of Koktem microdistrict in the village of inderbor

 

million tenge

Acceptance certificate

JSCB

231,8

231,8

205,4

RB

467003032

The total cost of the project is 4 470.9 million.tenge. Construction work began in 2018 and was completed in 2021

26,4

LB

467003028

2

Construction of a 48-apartment 4-storey house No. 2 in the Koktem microdistrict on site No. 11 in the village of inderbor

 

million tenge

Acceptance certificate

JSCB

255,1

255,1

255,1

RB

467003032

The total cost of the project is 4 469.8 million.tenge. Construction work began in 2018 and was completed in 2021.

3

Construction of a 48-apartment 4-storey residential building No. 3 on site No. 11 in Koktem microdistrict in the village of inderbor

 

million tenge

Acceptance certificate

JSCB

239,4

239,4

239,4

RB

467003032

The total cost of the project is 4 479.2 million.tenge. Construction work began in 2018 and was completed in 2021.

4.

Construction of a 48-apartment 4-storey residential building No. 4 from the Koktem microdistrict No. 11 in the village of inderbor

 

million tenge

Acceptance certificate

JSCB

266,8

266,8

264,0

RB

467003032

The total cost of the project is 4 480.5 million.tenge. Construction work began in 2018 and was completed in 2021.

2,8

LB

467003028

5

Construction of a five-storey residential building for 80 apartments (7.2) in the Koktem microdistrict of the village of inderbor

 

million tenge

Acceptance certificate

JSCB

522,3

522,3

113

RB

467003032

The total cost of the project is 1 1189.5 million.tenge. Construction work began in 2019 and was completed in 2021.

409

LB

467003028

6

Construction of a five-storey residential building for 80 apartments (7.1) in the Koktem microdistrict of the village of inderbor

 

million tenge

Acceptance certificate

JSCB

480

480

100

LB

467003034

Due to the 2-fold increase in the cost of building materials, the estimated documentation of the project was adjusted, 100.0 million tenge of these funds were disbursed, and 400.0 million tenge was returned to the budget.

7

Construction of a five-storey residential building for 80 apartments (8.1) in the Koktem microdistrict of the village of inderbor

 

 

million tenge

Acceptance certificate

JSCB

756

756

461,3

RB

467003032

The cost of the project is 1 1,133.4 million.tenge. Construction work began in 2021. The contract term is 2022.

8

Construction of engineering and communication infrastructure (gas supply)on the territory of Koktem microdistrict No. 11 of Inderbor settlement of inderbor district

 

 

 

million tenge

Acceptance certificate

JSCB

17,7

17,7

13,8

LB

467004028

The construction of the facility has been completed and accepted. According to the agreement, 13.8 million tenge out of 17.7 million tenge was disbursed. The remaining 3.9 million tenge was returned to the budget due to the non-consent of the institution «КазТрансГазАймақ» JSC, which owns the work on dismantling the existing iron pipe f219 mm.

9

Construction of engineering and communication infrastructure (Heat Supply)on the territory of Koktem microdistrict No. 11 of Inderbor settlement of inderbor district

 

 

 

million

tenge

Acceptance certificate

JSCB

29,4

29,4

29,4

RB

467004032

The total cost of the project is 3 332.7 million.tenge. Construction work began in 2019 and was completed in 2021.

10

Construction of water supply and sewerage networks at 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes)

 

million

tenge

Acceptance certificate

JSCB

15

15

15,0

LB

467004028

The total cost of the project is 1 18.0 million.tenge. Construction work began in 2019 and was completed in 2021.

11

Construction of highways and pedestrian paths (delivery to homes)at 11 sites in the Koktem microdistrict of the village of inderbor

 

million tenge

Acceptance certificate

JSCB

161,1

161,1

9,6

LB

467004028

The funds for 2021 have been fully disbursed. Due to incomplete allocation of funds, the construction period was extended until 2022.

12

Construction of heat supply for 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes)

 

million tenge

Acceptance certificate

JSCB

30,4

30,4

30,4

LB

467004028

The total cost of the project is 3 37.3 million.tenge. Construction work began in 2020 and was completed in 2021.

13

Construction of gas supply to 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes)

 

million tenge

Acceptance certificate

JSCB

2,6

2,6

1,6

LB

467004028

The construction of the facility has been completed and adopted. Due to the fact that the construction of a 4-row 48-apartment residential building was completed under the project, the funds for these works were returned to the budget in the amount of 1,022. 5 thousand tenge

14.

Construction of external networks (electricity, heat supply, water supply, sewerage, gas supply) and improvement of housing in the Koktem microdistrict of the village of inderbor in a five-storey residential building for 80 apartments (7.1)

 

 

million tenge

Acceptance certificate

JSCB

87,4

87,4

0

LB

467004015

In 2021, the construction of a residential building was not possible due to the fact that only earthmoving and concrete laying works were carried out. In this regard, the funds for 2021 were returned to the budget

15

Construction of external networks (electricity, heat supply, water supply, sewerage, gas supply) and improvement of housing in the Koktem microdistrict of the village of inderbor in a five-storey residential building for 80 apartments (8.1)

 

 

million tenge

Acceptance certificate

JSCB

127,2

127,2

0

LB

467004015

In 2021, the construction of a residential building was not possible due to the fact that only earthmoving and concrete laying works were carried out. In this regard, the funds for 2021 were returned to the budget

16.

Construction of engineering and communication infrastructure (mains system)in Akkala village, indersky district

 

million tenge

Acceptance certificate

JSCB

115,9

115,9

104,3

RB

467004032

The total cost of the project is 1 131.4 million.tenge. The funds for 2021 have been fully disbursed. The remaining 5% will be disbursed after the facility is commissioned for the current year.

17

Construction of engineering and communication infrastructure (mains system)in Eltay village, indersky district

 

million tenge

Acceptance certificate

JSCB

300,7

300,7

270,4

RB

467004032

The total cost of the project is 2 221.6 million.tenge. Construction work began and was completed in 2021. The remaining 5% will be disbursed after the facility is commissioned for the current year.

18

Construction of engineering and communication infrastructure (mains system)in Esbol village, indersky district

 

million tenge

Acceptance certificate

JSCB

153,9

153,9

138,4

RB

467004032

The total cost of the project is 1 121.4 million.tenge. Construction work began and was completed in 2021. The remaining 5% will be disbursed after the facility is commissioned for the current year.

19

Construction of engineering and communication infrastructure (water supply)on the territory of Akkala village (Right Bank) of indersky district

 

million tenge

Acceptance certificate

JSCB

1041,5

1041,5

952,6

RB

467004032

90% of the funds allocated from the Republican budget for 2021 have been fully disbursed. By the end of the work for the current year, the remaining 10% will be disbursed

20

Construction of engineering and communication infrastructure (mains system)in the village of Koktogay, indersky district

 

million tenge

Acceptance certificate

JSCB

52,5

52,5

0

LB

467004015

During the construction work, the connection point of the mains was provided in another project, and construction and installation work did not begin, as the project is still being developed. The funds for 2021 were returned to the budget.

21

Construction of engineering and communication infrastructure (gas supply)in the village of Koktogay, indersky district

 

million tenge

Acceptance certificate

JSCB

12,2

12,2

11,0

LB

467004028

The total cost of the project is 1 16.7 million.tenge. Construction work began and was completed in 2021.

22

Construction of engineering and communication infrastructure (water supply system)in the village of Koktogay, indersky district

 

million tenge

Acceptance certificate

JSCB

13,8

13,8

12,4

LB

467004015

Construction work began and was completed in 2021.

23.

Construction of engineering and communication infrastructure (mains system)in the village of Baudene, indersky district

 

million tenge

Acceptance certificate

JSCB

103,2

103,2

0

RB

467004011

No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year.

24

Construction of engineering and communication infrastructure in the village of Zharsuat indersky district

 

million tenge

Acceptance certificate

JSCB

64,4

64,4

0

RB

467004011

No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year.

 

25

Construction of engineering and communication infrastructure (MTS)in the village of Orlik, indersky district

 

million tenge

Acceptance certificate

JSCB

173,1

173,1

0

RB

467003011

No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year.

10. goal. Providing the population with high-quality drinking water, modernization of infrastructure facilities

12

Access of the population to water supply services

%

LEB

departmental report

ODIHR

100

100

100

*

*

13 settlements of the district are fully provided with clean water.

Completed.

The event

1

Replacement of membrane water filters for water treatment plants in rural localities

million tenge

LEB

departmental report

ODIHR

100

100

63,3

LB

492016000

At the expense of the regional budget, 63,297. 9 thousand tenge was allocated and fully disbursed for water treatment plants for autumn-winter works for 2021-2022

11. goal. Improving the condition of local roads

 

13

Share of local roads in good and satisfactory condition

%

LEB

departmental report

ODIHR

65,3

65,3

77,2

*

*

The length of local roads is 219.9 km, including highways in good and satisfactory condition-169.7 km, the share of which is 77.2%.

Completed.

The event

1

Major repairs of 12.9 km of intra-village access roads and pedestrian crossings in Koktogay village, Inder district, Atyrau region

Million tenge

Acceptance certificate

ODIHR

53,8

53,8

53,740

LB

492045000

The total cost of the project is 1 1,074.7 million.tenge. Major repairs began in 2020 and were completed in 2021

2

Major repairs of 12.5 km of intra-village highways and pedestrian crossings in the village of Eltay, Inder district, Atyrau region

 

Million tenge

information

ODIHR

77,6

77,6

77,592

LB

492045000

The total cost of the project is 1 1,545.1 million.tenge tenge. Major repairs began in 2020 and were completed in 2021

3

Major repairs of 10.8 km of intra-village highways and pedestrian crossings in Orlik village, Inder district, Atyrau region

Million tenge

Acceptance certificate

ODIHR

835,3

835,3

522,903

LB

492045000

The total cost of the project is 2 2,474.6 million. tenge. Major repairs began in 2021. The project completion date under the agreement is December 2022.

12. goal: to improve the environmental situation in the region

14

Share of processing and disposal of solid household waste

%

Statistical information

ODIHR

21

21

21,1

*

*

In January-December of this year, 6,684 tons of solid household waste were collected, 2,706 tons were removed to the landfill, and 570 tons or 21.1% were manually sorted. The annual plan has been implemented.

 

The event

1

Monitoring to ensure sanitary cleanliness of localities in the district

*

LEB

departmental report

ODIHR

*

*

*

*

*

In order to ensure sanitary cleanliness of settlements of the district, monthly monitoring is carried out.

13.Goal: level of provision of social benefits and services to rural localities

15

Level of provision of rural localities with social benefits and services in accordance with the system of regional standards

%

LEB

departmental report

District economic and financial department, JSCB, Agriculture, ODIHR,ABB, mayors of districts

74,9

74,9

75,7

*

*

The level of provision of social benefits and services in accordance with the system of regional standards of rural localities is as follows: Inderbor village-88.9%; Zharsuat, Quodene, Eltay, Esbol, Orlik and Koktogay villages – 84.2%; Yntymak and Akkala - 80 %; Aktan and Ketebay village – 50%; Kyzylzhar village -60; Construction Village -70%. The average score is 75.7%.

Completed.

The event

1

Monitoring of rural localities provided with social benefits and services in accordance with the system of regional standards

*

LEB

departmental report

District economic and financial department

*

*

*

*

*

In accordance with the system of regional standards of rural settlements, monitoring of localities provided with social benefits and services was carried out, the results of which were sent to the Regional Department of economy and budget planning.

2

Installation of a solid waste sorting complex at the landfill in the village of inderbor

Million tenge

Acceptance certificate

ODIHR

40,0

40,0

0

LB

492016000

In 2014, a land plot for a landfill of 3 hectares was determined and documents were issued. However, due to the expiration of the validity period of these documents, by the resolution of the regional akimat No. 117 dated April 29 of this year, they were issued for a new term with the right of temporary gratuitous land use until September 4, 2025. Currently, a State Act has been received for the land plot. At the same time, primary documents for the development of design and estimate documentation are currently being compiled. In December, a tender for determining the design contractor for the development of the POI will be submitted. After the POI has been developed and the expert opinion has been received, funds will be requested for the construction. Currently, 15 million tenge is allocated from the regional budget for the development of POI at two landfills. "I don't know," he said. In order to optimize waste sites, it is planned to install sorting units in the village of Inderbor and Esbol rural district in the district.

                             

 

 

 

 

 

 

 

 

 

 

 

 

  1. Development of financial resources

Source of funding

Plan, million tenge

Fact, million tenge

Reasons for not using

 

1

2

3

4

 

Priority development of non-resource industries

 

Other sources

10

553,3

 

 

Total

10

553,3

 

 

Improving the competitiveness of agribusiness sectors

 

Other sources

1,1

1,2

 

 

Total

1,1

1,2

 

 

Ensuring employment and creating new jobs

 

 

 

Republican budget

85,1

85,1

 

 

Local budget

80,0

80,0

 

 

Total

165,1

165,1

 

 

Ensuring the quality of services of general secondary education and pre-school education

 

Local budget

1145,8

233,2

 

 

Total

1145,8

233,2

 

 

Increasing the availability of social infrastructure facilities for citizens

 

Republican budget

428

385,1

 

 

Local budget

724

346,2

 

 

Total

1152

731,3

 

 

Increasing the pace of housing construction to ensure housing affordability for citizens

 

Republican budget

4253,5

3033,3

 

 

Local budget

999,7

618

 

 

Total

5253,2

3651,3

 

 

Providing the population with high-quality drinking water, modernization of infrastructure facilities

 

Local budget

100

63,3

 

 

Total

100

63,3

 

 

Improving the condition of local roads

 

Local budget

966,7

654,2

 

 

Total

966,7

654,2

 

 

Total:

8 793,9

6 052,9

 

 

 

 

  1. Analytical note

            Priority development of non-resource industries. According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars. According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars. In the reporting year «ГИПС ИНДЕР» LLP invested млн 235.8 million in the production of dry building mixes and building gypsum.investments in the amount of tenge are attracted.

            Improving the competitiveness of agro-industrial sectors. In the reporting year, the volume of gross agricultural output amounted to 11 billion US dollars. 512 million.Tenge, the physical volume index is 104.1%.In 2020, 11 farms with a total area of 1,545 hectares were engaged in increasing the share of crop production, including drip irrigation, including 471 hectares by drip method. In 2021, 1,590 hectares were allocated for the entire crop, of which 779 hectares, i.e. 49%, were irrigated by drip method by 17 farms. For animal husbandry, it is planned to develop a fund to increase the area under forage crops to 490 hectares, and in the reporting year-to 500 hectares. In order to update the agricultural machinery fleet, 13 units of agricultural machinery and equipment (tractors and aggregates)were purchased in the reporting year. These are" Dastan " - 1," ER Tostik "- 1, farm"Asyl Agro "-2, individual entrepreneurs"Esmagambetov "-2,"Zhalgasbayev "-2,"Uteshov" -2, multi-specialty agricultural college Inder-1, LLP" Kaztatservis " - 1. in addition, 17 farms purchased drip irrigation equipment, 4 farms purchased sprinkler irrigation equipment.

            Ensuring employment and creating new jobs. In 2021, it is planned to create 1,271 new jobs in the district. By the end of the year, 1,758 new jobs were created in the district (including 869 permanent and 889 temporary). "In particular, 45 people were created within the framework of the state programs" "employment roadmap for 2020-2021"", 99 places - within the framework of the housing construction program" "Nurly zher"", 805 places - within the framework of the program ""Enbek"", 22 places - under the program ""Auyl El besigi"", 581 places - at employers of the district, since the beginning of the year 206 new entrepreneurs have been registered in the tax department.

            In the district, from January 1 to December 31, 2021, the number of recipients of social assistance (conditional monetary assistance) was 542 people, including 374 able-bodied people, the share of able-bodied people among recipients of targeted social assistance was 69.0%.

            Ensuring the quality of services of general secondary education and pre-school education. According to the state program for the development of education in the Republic of Kazakhstan for 2021-2025, approved by the decree of the head of state, the quality of education is growing every year.

            The secondary school named after K. Eskaliyev in the village of esbol was recognized as an emergency school based on the conclusion of "Techexpert-Eco" LLP No. 00266 dated February 12, 2017. Currently, construction of a school for 320 children is underway in Esbol village. The contractor is "Ondasyn Stroy" LLP.There is no three-shift school.

            The number of children with disabilities enrolled in general education schools determined by the medical, pedagogical and psychological expert commission for health reasons in the district is 154. of these, 146 children with special educational needs are covered in 12 out of 15 schools. On April 23, 2021, the Regional Department of Education sent 2 Budget applications for the necessary equipment for creating inclusive conditions in schools. However, no funds were allocated.

            Increasing the availability of social infrastructure facilities for citizens. In recent years, special attention has been paid to the development of Physical Culture and sports in the country. The main goal in this area is to promote the health of young people by leading a healthy lifestyle. Bukhara mass sports events were held jointly with akims and institutions of the district to promote sports among young people, show the importance and specifics of sports. In 2021, 373.7 million tenge was allocated from the Republican budget for the project "Auyl El besigi", the construction of a sports complex in the village of Zharsuat is being completed, and the construction of a sports complex in the village of Koktogay continues. 195 million tenge was allocated from the local budget for the purchase of the building of the Sports Complex in the village of Orlik and transferred to the balance sheet of the Department of Physical Culture and sports of Atyrau region. In 2021, 3 sports grounds were put into operation. These are a sports field in the KSU "secondary school named after sh.Ualikhanov" in the village of inderbor, a sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor, and a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor.

            Increase the pace of housing construction to ensure housing affordability for citizens. According to the results of 2020, the total housing stock was 669,735.5 sq. m., and in January –December 2021, 462 apartments with an additional area of 53,338 sq. m. were put into operation. The total housing stock in the reporting year was 723,073.5 sq. m.and 22.2 sq.m. per person.. (population-32545).

            The number of multi – row residential buildings in the district is 64, of which the number of dilapidated housing is 19, or 29.6%. Due to the fact that the housing commissioned in the reporting year is planned to be transferred to the categories of large families and low-income families, it is not possible to move the housing recognized as dilapidated. No funds were allocated for the construction or purchase of housing in this category.

            Providing the population with high-quality drinking water, modernization of infrastructure facilities. 13 settlements of the district are fully provided with clean water. For 2021-2022, 63,297.9 thousand tenge was allocated and fully disbursed at the expense of the regional budget for water treatment plants for autumn-winter work.

             Improving the condition of local roads. The length of local roads is 219.9 km, including highways in good and satisfactory condition-169.7 km, the share of which is 77.2%. During the reporting year, 131.3 million US dollars were spent at the expense of the local budget to complete major repairs of intra-village access roads and pedestrian crossings in the settlements of Koktogay and Eltay.the funds were allocated and fully disbursed. Major repairs of 10.8 km of intra-village highways and pedestrian paths in Orlik village will be completed under the contract in December 2022.

            Improving the environmental situation in the region. In January-December of this year, 6,684 tons of solid household waste were collected, 2,706 tons were removed to the landfill, and 570 tons or 21.1% were manually sorted.

            The level of provision of social benefits and services to rural localities. The level of provision of social benefits and services in rural localities in accordance with the system of regional standards is 75.7%. In particular, in the settlements: Inderbor – 88.9%; Zharsuat, Quodene, Eltay, Esbol, Orlik and Koktogay – 84.2%; Yntymak and Akkala - 80 %; Aktan and Ketebay – 50%; Kyzylzhar -60%; Kurylys-70%.

 

 

 

 

 