Methodology for monitoring the Strategic Development Plan of the Republic of Kazakhstan, state and government programs, strategic plans of government agencies and territorial development programs Appendix 2 Object |
Report on the implementation of the Territorial Development Program of Inder district for 2021-2025
Reporting period ____2021__________
Approved by the decision of the district maslikhat №-6-VІІ of January 15, 2021
State body Inder district department of economy and finance
|
№ |
Name |
Unit of measurement |
Source of information |
Responsible executors |
Execution |
Source of funding |
Budget program code |
Execution information |
||||||
|
Basic (initial) value |
plan |
fact |
||||||||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
||||
|
І. Regional economic growth |
||||||||||||||
|
1.Goal: Priority development of non-resource industries |
||||||||||||||
|
1. |
Investments in fixed assets in the manufacturing industry |
mil. tenge |
Statistical information |
VCT |
10 |
10 |
553,3 |
OS |
* |
According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars Completed |
||||
|
Events |
||||||||||||||
|
1 |
Attracting investments in fixed assets with" TҰЗ" LLP for the production of table salt and the implementation of a plant for the production of technical salt |
mil. tenge |
Information from «ТҰЗ» LLP |
VCT |
5 |
5 |
0 |
OS |
* |
The project to open a plant for the production of table salt has been postponed to 2022. The reason is that due to the quarantine situation, the necessary equipment from foreign countries was not received on time. |
||||
|
2 |
Attracting investments in fixed assets for the implementation of a plant for the production of dry building mixes with «ИСИГипсИндер» LLP |
mil. tenge |
Information from «ИСИГипсИндер» LLP |
VCT |
5 |
5 |
317,5 |
OS |
|
In the reporting year «ИСИГипсИндер» LLP invested млн 317.5 million in the implementation of the plant for the production of dry building mixes. investments in the amount of tenge were attracted, new jobs were created, 4 people were employed. |
||||
|
3 |
Attracting investments for the production of dry building mixes, building gypsum with «ИСИГипсИндер» LLP |
mil. tenge |
Information from «ИСИГипсИндер» LLP |
VCT |
|
|
235,8 |
OS |
|
In the reporting year, «ИСИГипсИндер» LLP invested млн 235.8 million in the production of dry building mixes and building gypsum.investments in the amount of tenge are attracted. |
||||
|
2 Goal: Improving the competitiveness of agro-industrial sectors |
||||||||||||||
|
2 |
Index of physical volume of gross agricultural output |
% |
Official statistics |
Agriculture |
102,7 |
102,7 |
104,1 |
* |
* |
The volume of gross agricultural output in the reporting year amounted to 11 Millard 512 million Tenge, the physical volume index is 104.1%. Completed |
||||
|
3 |
The share of increasing the volume of crops, including increasing the share of drip irrigation methods |
% |
LB departmental report |
Agriculture |
49 |
49 |
49 |
* |
* |
In 2020, 11 farms were engaged in drip irrigation with a total area of 1545 hectares, of which 471 hectares. In 2021, 1,590 hectares were allocated for the entire crop, of which 779 hectares, or 49%, were irrigated by drip method by 17 farms. Completed |
||||
|
Events |
||||||||||||||
|
1 |
Development of a fund for increasing the area under forage crops to 490 hectares for animal husbandry |
Ga |
LB departmental report |
Agriculture |
440 |
440 |
500 |
* |
* |
For animal husbandry,the area under which forage crops are sown is 500 hectares |
||||
|
2 |
Purchase of 47 new agricultural machinery and equipment in order to update the agricultural machinery fleet |
unit |
LEB departmental report |
Agriculture |
12 |
12 |
12 |
* |
* |
In the reporting year, 13 units of agricultural machinery and equipment (tractors and aggregates)were purchase. These are" Dastan " - 1," ER Tostik "- 1, peasant farm"Asyl Agro "-2, individual entrepreneurs"Esmagambetov "-2,"Zhalgasbayev "-2,"Uteshov "-2,multi-specialty agricultural college Inder-1, LLP" Kaztatservice " - 1. |
||||
|
3 |
Purchase of drip irrigation equipment by economic entities |
unit |
LEB departmental report |
Agriculture |
12 |
12 |
21 |
|
|
In the reporting year, 17 farms purchased drip irrigation equipment, and 4 farms purchased sprinkler irrigation equipment. |
||||
|
mil. tenge |
1,1 |
1,1 |
1,2 |
OS |
|
|||||||||
|
THE SECOND DIRECTION: Ensuring a new quality of life |
||||||||||||||
|
3. Goal: Ensuring employment and creating new jobs |
||||||||||||||
|
4 |
Number of jobs created, including |
unit |
LEB report |
ODIHR |
1271 |
1271 |
1758 |
|
* |
By the end of 2021, 1,758 new jobs were created in the district (including 869 permanent and 889 temporary). "In particular, within the framework of the state programs" "employment roadmap for 2020-2021" "45 people, within the framework of the housing construction program" "Nurly zher ""- 99 places, within the framework of the program ""Enbek ""- 805 places, under the program ""Auyl El besigi "" - 22 places, employers of the district - 581 places, since the beginning of the year 206 new entrepreneurs have been registered in the tax administration." Completed |
||||
|
permanent |
551 |
551 |
869 |
|
||||||||||
|
temporary |
720 |
720 |
889 |
|
||||||||||
|
5 |
Share of employed recipients of able-bodied TSA (conditional monetary assistance) and those involved in active employment promotion measures (in the total number of able-bodied recipients of the TSA) |
% |
LEB report |
ODIHR |
69,0 |
69,0 |
69,0 |
|
|
In the district, from January 1 to December 31, 2021, the number of recipients of social assistance (conditional monetary assistance) was 542 people, including 374 able-bodied people, the share of able-bodied people among recipients of targeted social assistance was 69.0%. Completed |
||||
|
The event |
||||||||||||||
|
1 |
«ИСИГипсИндер» LLP and" Inder TUZ COMPANY " LLP create new jobs by expanding their currently operating factories to provide employment for unemployed citizens on the ground |
* |
VCT |
ODIHR |
* |
* |
* |
* |
* |
«ИСИГипсИндер» LLP has completed the expansion of the plant, created new jobs and employed 5 people. Due to the incomplete expansion of the existing plant of INDER TUZ COMPANY LLP, no new jobs were created
|
||||
|
2 |
Attracting local unemployed citizens to short-term training courses in specialties necessary for plant expansion projects |
* |
ODIHR Department statistical reports 1T and 2T |
ODIHR
|
* |
* |
* |
* |
* |
Since the beginning of the year, 57 people from among the unemployed registered in the District Employment Center have been sent to short-term courses. |
||||
|
3 |
Placement of unemployed citizens for new jobs at the facilities under construction through the implementation of a project for the construction of schools, kindergartens and sports complexes in rural areas |
* |
ODIHR Department information |
ODIHR, akims of settlements and rural districts |
* |
* |
* |
* |
* |
In 2021, under the program" Auyl-El besigi", 22 people were sent to 3 projects in the District ( major repairs of street lighting in Yntymak village, construction of a sports and Recreation Complex in Koktogay village, construction of a sports and Recreation Complex in Zharsuat village), 47 people were employed in 1 project under the program" Employment roadmap " (construction of a secondary school named after K. Eskaliyev in Esbol village). In total, in 2021, 4 projects were implemented, and 69 unemployed citizens of the district were employed in the created jobs. |
||||
|
4 |
Holding job fairs with employers |
* |
ODIHR reporting of the Department |
ODIHR, akims of settlements and rural districts |
* |
* |
* |
* |
* |
In 2021, 4 job fairs were held in the district, 181 of the 342 people who took part in the Fair were provided with permanent jobs |
||||
|
5 |
Public Works |
million tenge |
ODIHR reporting of the Department |
ODIHR, akims of settlements and rural districts |
112,0 |
123,2 |
123,2 |
|
|
Since the beginning of the year, it is planned to send 560 people to paid public works, by the end of the year, 40 people have been allocated additional funds at the expense of the local budget in the amount of 5.3 million tenge, and 600 people have been sent to work. At the end of the term, 248 people were employed on a permanent basis. For 2021, 112.0 million tenge was approved for this program, and during the year it increased by 123.2 million tenge. |
||||
|
22,0 |
43,2 |
43,2 |
RB |
801004011
|
||||||||||
|
90,0 |
80,0 |
80,0 |
LB |
801004100 |
||||||||||
|
6. |
Youth practice |
million tenge |
ODIHR reporting of the Department |
ODIHR
|
30,6 |
20,1 |
20,1 |
RB |
801004011
|
According to the program" youth practice", 70 young professionals were sent to institutions of the district for a 6-month internship, as a result of which 47 young people were provided with permanent jobs. For 2021, 30.6 million tenge was allocated for this program. at the end of the year, funds in the amount of KZT 10.5 million were approved. the funds in the amount of KZT 20.1 million were transferred to the state grant and updated. the tenge is fully disbursed. |
||||
|
7 |
Social work |
million tenge |
ODIHR reporting of the Department |
ODIHR, akims of settlements and rural districts |
22,9 |
21,8 |
21,8 |
RB |
801004011
|
In 2021, it is planned to employ 90 people in social jobs, and 100 people took part in the program. As a result, 78 people are provided with permanent jobs. For 2021, funds in the amount of 22.9 million tenge were approved for this program, and 21.8 million tenge was specified |
||||
|
4. goal. Ensuring the quality of services of general secondary education and pre-school education |
||||||||||||||
|
6 |
Reduction of the number of emergency and three-way schools, including |
unit |
Conclusion of the National Center of «Құрылыс консалтинг» JSC |
ABB, JSCB |
1/0 |
1/0 |
1/0 |
* |
* |
K. Eskaliyev in esbol village secondary school named after In 2017, it was recognized as an emergency school. Currently, construction of a school for 320 children is underway in Esbol village. The contractor is "Ondasyn Stroy" LLP. There is no three-shift school Completed |
||||
|
Emergency |
||||||||||||||
|
Three-shift |
||||||||||||||
|
7 |
Share of schools that have created conditions for Inclusive Education |
% |
LEB report |
ABB |
80,0 |
80,0 |
|
* |
* |
The number of children with disabilities enrolled in general education schools determined by the medical, pedagogical and psychological expert commission for health reasons in the district is 154. of these, 146 children with special educational needs are covered in 12 out of 15 schools. On April 23, 2021, the Regional Department of Education sent 2 Budget applications for the necessary equipment for creating inclusive conditions in schools. However, no funds were allocated. Therefore, the indicator is not implemented according to the plan. Failed |
||||
|
The event |
||||||||||||||
|
1 |
Construction of a school for 320 children in Esbol village, Inder distric |
million tenge |
Acceptance certificate |
ABB, JSCB |
1 145,8 |
1 145,8 |
233,2 |
LB |
271086 |
According to the results of 2021, 233 million 228 thousand 160 tenge was disbursed. |
||||
|
2 |
The presence of raised (tactile) stripes on the stairs |
million tenge |
acceptance certificate |
ABB |
0,300 |
0,300 |
0 |
LB |
261067 |
The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated |
||||
|
3 |
Sink and toilet equipment for children with musculoskeletal disorders and visual impairments |
million tenge |
acceptance certificate |
ABB |
0,5 |
0,5 |
0 |
LB |
261082 |
The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated |
||||
|
4 |
Functional desks, tables for children with cerebral palsy |
million tenge |
acceptance certificate |
ABB |
1,0 |
1,0 |
0 |
LB |
261082 |
The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated |
||||
|
5 |
Lamps for children with visual impairments |
million tenge |
acceptance certificate |
ABB |
0,3 |
0,3 |
0 |
LB |
261067 |
The budget application was sent to the Regional Department of Education 2 times. However, no funds were allocated |
||||
|
6 |
Organization of subject Olympiads, creative art competitions for children with disabilities |
* |
LEB departmental report |
ABB |
* |
* |
* |
* |
* |
|
||||
|
5. goal: to increase the availability of social infrastructure facilities for citizens |
||||||||||||||
|
8 |
Provision of sports infrastructure per 1000 people |
% |
Stat information and AMTDDShSB |
AMTDDShSB |
21,3 |
21,3 |
21,3 |
* |
* |
In the District, 3 sports complexes, a wrestling hall, a Sports Hall of 16 educational organizations, 1 shooting range and a Sports Hall of a multidisciplinary Agricultural College serve the population. The total area is 6676.9 square meters. Sports infrastructure is provided by 21.3% per 1000 people of the population. Completed |
||||
|
The event |
||||||||||||||
|
1 |
Construction of a sports complex in the village of Zharsuat |
million tenge |
* |
DShSB |
228,0 |
228,0 |
203,0 |
RB |
467079028 |
In 2021, 203.0 tenge was allocated from the Republican budget for the work of the zharsuat Sports Complex. The work of the Sports Complex is completed by 90%. It is expected to be commissioned by the first quarter of 2022 |
||||
|
2 |
Construction of a sports complex in Koktogay village |
million tenge |
* |
JSCB |
200,0 |
200,0 |
170,7 |
RB |
467079032 |
Construction of Sports Complex in koktogay village continue |
||||
|
3 |
Purchase of a sports complex building in Orlik village |
million tenge |
* |
JSCB |
195,0 |
195,0 |
195,0 |
LB |
467008015 |
The building of the Sports Complex in the village of Orlik was transferred to the balance sheet of the Department of Physical Culture and sports of Atyrau region |
||||
|
4 |
Construction of a sports field in the KSU "secondary school named after sh.Ualikhanov" in the village of inderbo |
million tenge |
* |
JSCB |
35,9 |
35,9 |
35,9 |
LB |
467008028 |
In 2021, the sports ground of the secondary school named after sh. Ualikhanov was put into operation.. |
||||
|
5 |
Construction of a sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor |
million tenge |
* |
JSCB |
15,3 |
15,3 |
15,3 |
LB |
467008028 |
A sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor has been adopted |
||||
|
6 |
Construction of a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor |
million tenge |
* |
JSCB |
200,0 |
200,0 |
11,4 |
RB |
467079032 |
The construction of a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor has been completed and put into operation. The balance was transferred to the school |
||||
|
100 |
LB |
467008028 |
||||||||||||
|
7 |
Construction of a sports field in KSU "Koktem Kazakh Secondary School" in the village of inderbor |
million tenge |
* |
JSCB |
123,8 |
123,8 |
- |
LB |
467008015 |
Budget applications were sent to the Construction Department of Atyrau region. Construction will begin at the time when the funds are provided |
||||
|
8 |
Construction of a sports field in the KSU "secondary school named after M. Auezov" in the village of inderbor |
million tenge |
* |
JSCB |
154,0 |
154,0 |
|
LB |
467008015 |
Budget applications were sent to the Construction Department of Atyrau region. Construction will begin at the time when the funds are provided. |
||||
|
Third direction: a comfortable and safe area for living |
||||||||||||||
|
7. goal: to increase the pace of housing construction to ensure housing affordability for citizens |
||||||||||||||
|
10 |
Provision of Housing per inhabitant |
sq.m per person |
Official statistics |
ODIHR |
22,2 |
22,2 |
22,2 |
* |
* |
According to the results of 2020, the total housing stock was 669,735.5 sq. m., and in January –December 2021, 462 apartments with an additional area of 53,338 sq. m. were put into operation. The total housing stock in the reporting year was 723,073.5 sq. m.and 22.2 sq.m. per person.. (population – 32545) Completed. |
||||
|
11 |
Share of reducing the number of Emergency Multi-storey residential buildings |
* |
LEB departmental report |
ODIHR |
25,3 |
25,3 |
29,6 |
* |
* |
The number of multi – row residential buildings in the district is 64, of which the number of dilapidated housing is 19, or 29.6%. Due to the fact that the housing commissioned in the reporting year is planned to be transferred to the categories of large families and low-income families, it is not possible to move the housing recognized as dilapidated. No funds were allocated for the construction or purchase of housing in this category. Not done. |
||||
|
The event |
||||||||||||||
|
1 |
Construction of a 48-apartment 4-storey residential building No. 1 On Site No. 11 of Koktem microdistrict in the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
231,8 |
231,8 |
205,4 |
RB |
467003032 |
The total cost of the project is 4 470.9 million.tenge. Construction work began in 2018 and was completed in 2021 |
||||
|
26,4 |
LB |
467003028 |
||||||||||||
|
2 |
Construction of a 48-apartment 4-storey house No. 2 in the Koktem microdistrict on site No. 11 in the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
255,1 |
255,1 |
255,1 |
RB |
467003032 |
The total cost of the project is 4 469.8 million.tenge. Construction work began in 2018 and was completed in 2021. |
||||
|
3 |
Construction of a 48-apartment 4-storey residential building No. 3 on site No. 11 in Koktem microdistrict in the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
239,4 |
239,4 |
239,4 |
RB |
467003032 |
The total cost of the project is 4 479.2 million.tenge. Construction work began in 2018 and was completed in 2021. |
||||
|
4. |
Construction of a 48-apartment 4-storey residential building No. 4 from the Koktem microdistrict No. 11 in the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
266,8 |
266,8 |
264,0 |
RB |
467003032 |
The total cost of the project is 4 480.5 million.tenge. Construction work began in 2018 and was completed in 2021. |
||||
|
2,8 |
LB |
467003028 |
||||||||||||
|
5 |
Construction of a five-storey residential building for 80 apartments (7.2) in the Koktem microdistrict of the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
522,3 |
522,3 |
113 |
RB |
467003032 |
The total cost of the project is 1 1189.5 million.tenge. Construction work began in 2019 and was completed in 2021. |
||||
|
409 |
LB |
467003028 |
||||||||||||
|
6 |
Construction of a five-storey residential building for 80 apartments (7.1) in the Koktem microdistrict of the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
480 |
480 |
100 |
LB |
467003034 |
Due to the 2-fold increase in the cost of building materials, the estimated documentation of the project was adjusted, 100.0 million tenge of these funds were disbursed, and 400.0 million tenge was returned to the budget. |
||||
|
7 |
Construction of a five-storey residential building for 80 apartments (8.1) in the Koktem microdistrict of the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
756 |
756 |
461,3 |
RB |
467003032 |
The cost of the project is 1 1,133.4 million.tenge. Construction work began in 2021. The contract term is 2022. |
||||
|
8 |
Construction of engineering and communication infrastructure (gas supply)on the territory of Koktem microdistrict No. 11 of Inderbor settlement of inderbor district |
million tenge |
Acceptance certificate |
JSCB |
17,7 |
17,7 |
13,8 |
LB |
467004028 |
The construction of the facility has been completed and accepted. According to the agreement, 13.8 million tenge out of 17.7 million tenge was disbursed. The remaining 3.9 million tenge was returned to the budget due to the non-consent of the institution «КазТрансГазАймақ» JSC, which owns the work on dismantling the existing iron pipe f219 mm. |
||||
|
9 |
Construction of engineering and communication infrastructure (Heat Supply)on the territory of Koktem microdistrict No. 11 of Inderbor settlement of inderbor district |
million tenge |
Acceptance certificate |
JSCB |
29,4 |
29,4 |
29,4 |
RB |
467004032 |
The total cost of the project is 3 332.7 million.tenge. Construction work began in 2019 and was completed in 2021. |
||||
|
10 |
Construction of water supply and sewerage networks at 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes) |
million tenge |
Acceptance certificate |
JSCB |
15 |
15 |
15,0 |
LB |
467004028 |
The total cost of the project is 1 18.0 million.tenge. Construction work began in 2019 and was completed in 2021. |
||||
|
11 |
Construction of highways and pedestrian paths (delivery to homes)at 11 sites in the Koktem microdistrict of the village of inderbor |
million tenge |
Acceptance certificate |
JSCB |
161,1 |
161,1 |
9,6 |
LB |
467004028 |
The funds for 2021 have been fully disbursed. Due to incomplete allocation of funds, the construction period was extended until 2022. |
||||
|
12 |
Construction of heat supply for 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes) |
million tenge |
Acceptance certificate |
JSCB |
30,4 |
30,4 |
30,4 |
LB |
467004028 |
The total cost of the project is 3 37.3 million.tenge. Construction work began in 2020 and was completed in 2021. |
||||
|
13 |
Construction of gas supply to 11 sites in Koktem microdistrict in the village of inderbo (delivery to homes) |
million tenge |
Acceptance certificate |
JSCB |
2,6 |
2,6 |
1,6 |
LB |
467004028 |
The construction of the facility has been completed and adopted. Due to the fact that the construction of a 4-row 48-apartment residential building was completed under the project, the funds for these works were returned to the budget in the amount of 1,022. 5 thousand tenge |
||||
|
14. |
Construction of external networks (electricity, heat supply, water supply, sewerage, gas supply) and improvement of housing in the Koktem microdistrict of the village of inderbor in a five-storey residential building for 80 apartments (7.1) |
million tenge |
Acceptance certificate |
JSCB |
87,4 |
87,4 |
0 |
LB |
467004015 |
In 2021, the construction of a residential building was not possible due to the fact that only earthmoving and concrete laying works were carried out. In this regard, the funds for 2021 were returned to the budget |
||||
|
15 |
Construction of external networks (electricity, heat supply, water supply, sewerage, gas supply) and improvement of housing in the Koktem microdistrict of the village of inderbor in a five-storey residential building for 80 apartments (8.1) |
million tenge |
Acceptance certificate |
JSCB |
127,2 |
127,2 |
0 |
LB |
467004015 |
In 2021, the construction of a residential building was not possible due to the fact that only earthmoving and concrete laying works were carried out. In this regard, the funds for 2021 were returned to the budget |
||||
|
16. |
Construction of engineering and communication infrastructure (mains system)in Akkala village, indersky district |
million tenge |
Acceptance certificate |
JSCB |
115,9 |
115,9 |
104,3 |
RB |
467004032 |
The total cost of the project is 1 131.4 million.tenge. The funds for 2021 have been fully disbursed. The remaining 5% will be disbursed after the facility is commissioned for the current year. |
||||
|
17 |
Construction of engineering and communication infrastructure (mains system)in Eltay village, indersky district |
million tenge |
Acceptance certificate |
JSCB |
300,7 |
300,7 |
270,4 |
RB |
467004032 |
The total cost of the project is 2 221.6 million.tenge. Construction work began and was completed in 2021. The remaining 5% will be disbursed after the facility is commissioned for the current year. |
||||
|
18 |
Construction of engineering and communication infrastructure (mains system)in Esbol village, indersky district |
million tenge |
Acceptance certificate |
JSCB |
153,9 |
153,9 |
138,4 |
RB |
467004032 |
The total cost of the project is 1 121.4 million.tenge. Construction work began and was completed in 2021. The remaining 5% will be disbursed after the facility is commissioned for the current year. |
||||
|
19 |
Construction of engineering and communication infrastructure (water supply)on the territory of Akkala village (Right Bank) of indersky district |
million tenge |
Acceptance certificate |
JSCB |
1041,5 |
1041,5 |
952,6 |
RB |
467004032 |
90% of the funds allocated from the Republican budget for 2021 have been fully disbursed. By the end of the work for the current year, the remaining 10% will be disbursed |
||||
|
20 |
Construction of engineering and communication infrastructure (mains system)in the village of Koktogay, indersky district |
million tenge |
Acceptance certificate |
JSCB |
52,5 |
52,5 |
0 |
LB |
467004015 |
During the construction work, the connection point of the mains was provided in another project, and construction and installation work did not begin, as the project is still being developed. The funds for 2021 were returned to the budget. |
||||
|
21 |
Construction of engineering and communication infrastructure (gas supply)in the village of Koktogay, indersky district |
million tenge |
Acceptance certificate |
JSCB |
12,2 |
12,2 |
11,0 |
LB |
467004028 |
The total cost of the project is 1 16.7 million.tenge. Construction work began and was completed in 2021. |
||||
|
22 |
Construction of engineering and communication infrastructure (water supply system)in the village of Koktogay, indersky district |
million tenge |
Acceptance certificate |
JSCB |
13,8 |
13,8 |
12,4 |
LB |
467004015 |
Construction work began and was completed in 2021. |
||||
|
23. |
Construction of engineering and communication infrastructure (mains system)in the village of Baudene, indersky district |
million tenge |
Acceptance certificate |
JSCB |
103,2 |
103,2 |
0 |
RB |
467004011 |
No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year. |
||||
|
24 |
Construction of engineering and communication infrastructure in the village of Zharsuat indersky district |
million tenge |
Acceptance certificate |
JSCB |
64,4 |
64,4 |
0 |
RB |
467004011 |
No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year.
|
||||
|
25 |
Construction of engineering and communication infrastructure (MTS)in the village of Orlik, indersky district |
million tenge |
Acceptance certificate |
JSCB |
173,1 |
173,1 |
0 |
RB |
467003011 |
No funds were allocated for construction and installation works for 2021. Budget applications were sent to the Construction Department of Atyrau region for the current year. |
||||
|
10. goal. Providing the population with high-quality drinking water, modernization of infrastructure facilities |
||||||||||||||
|
12 |
Access of the population to water supply services |
% |
LEB departmental report |
ODIHR |
100 |
100 |
100 |
* |
* |
13 settlements of the district are fully provided with clean water. Completed. |
||||
|
The event |
||||||||||||||
|
1 |
Replacement of membrane water filters for water treatment plants in rural localities |
million tenge |
LEB departmental report |
ODIHR |
100 |
100 |
63,3 |
LB |
492016000 |
At the expense of the regional budget, 63,297. 9 thousand tenge was allocated and fully disbursed for water treatment plants for autumn-winter works for 2021-2022 |
||||
|
11. goal. Improving the condition of local roads |
||||||||||||||
|
13 |
Share of local roads in good and satisfactory condition |
% |
LEB departmental report |
ODIHR |
65,3 |
65,3 |
77,2 |
* |
* |
The length of local roads is 219.9 km, including highways in good and satisfactory condition-169.7 km, the share of which is 77.2%. Completed. |
||||
|
The event |
||||||||||||||
|
1 |
Major repairs of 12.9 km of intra-village access roads and pedestrian crossings in Koktogay village, Inder district, Atyrau region |
Million tenge |
Acceptance certificate |
ODIHR |
53,8 |
53,8 |
53,740 |
LB |
492045000 |
The total cost of the project is 1 1,074.7 million.tenge. Major repairs began in 2020 and were completed in 2021 |
||||
|
2 |
Major repairs of 12.5 km of intra-village highways and pedestrian crossings in the village of Eltay, Inder district, Atyrau region |
Million tenge |
information |
ODIHR |
77,6 |
77,6 |
77,592 |
LB |
492045000 |
The total cost of the project is 1 1,545.1 million.tenge tenge. Major repairs began in 2020 and were completed in 2021 |
||||
|
3 |
Major repairs of 10.8 km of intra-village highways and pedestrian crossings in Orlik village, Inder district, Atyrau region |
Million tenge |
Acceptance certificate |
ODIHR |
835,3 |
835,3 |
522,903 |
LB |
492045000 |
The total cost of the project is 2 2,474.6 million. tenge. Major repairs began in 2021. The project completion date under the agreement is December 2022. |
||||
|
12. goal: to improve the environmental situation in the region |
||||||||||||||
|
14 |
Share of processing and disposal of solid household waste |
% |
Statistical information |
ODIHR |
21 |
21 |
21,1 |
* |
* |
In January-December of this year, 6,684 tons of solid household waste were collected, 2,706 tons were removed to the landfill, and 570 tons or 21.1% were manually sorted. The annual plan has been implemented.
|
||||
|
The event |
||||||||||||||
|
1 |
Monitoring to ensure sanitary cleanliness of localities in the district |
* |
LEB departmental report |
ODIHR |
* |
* |
* |
* |
* |
In order to ensure sanitary cleanliness of settlements of the district, monthly monitoring is carried out. |
||||
|
13.Goal: level of provision of social benefits and services to rural localities |
||||||||||||||
|
15 |
Level of provision of rural localities with social benefits and services in accordance with the system of regional standards |
% |
LEB departmental report |
District economic and financial department, JSCB, Agriculture, ODIHR,ABB, mayors of districts |
74,9 |
74,9 |
75,7 |
* |
* |
The level of provision of social benefits and services in accordance with the system of regional standards of rural localities is as follows: Inderbor village-88.9%; Zharsuat, Quodene, Eltay, Esbol, Orlik and Koktogay villages – 84.2%; Yntymak and Akkala - 80 %; Aktan and Ketebay village – 50%; Kyzylzhar village -60; Construction Village -70%. The average score is 75.7%. Completed. |
||||
|
The event |
||||||||||||||
|
1 |
Monitoring of rural localities provided with social benefits and services in accordance with the system of regional standards |
* |
LEB departmental report |
District economic and financial department |
* |
* |
* |
* |
* |
In accordance with the system of regional standards of rural settlements, monitoring of localities provided with social benefits and services was carried out, the results of which were sent to the Regional Department of economy and budget planning. |
||||
|
2 |
Installation of a solid waste sorting complex at the landfill in the village of inderbor |
Million tenge |
Acceptance certificate |
ODIHR |
40,0 |
40,0 |
0 |
LB |
492016000 |
In 2014, a land plot for a landfill of 3 hectares was determined and documents were issued. However, due to the expiration of the validity period of these documents, by the resolution of the regional akimat No. 117 dated April 29 of this year, they were issued for a new term with the right of temporary gratuitous land use until September 4, 2025. Currently, a State Act has been received for the land plot. At the same time, primary documents for the development of design and estimate documentation are currently being compiled. In December, a tender for determining the design contractor for the development of the POI will be submitted. After the POI has been developed and the expert opinion has been received, funds will be requested for the construction. Currently, 15 million tenge is allocated from the regional budget for the development of POI at two landfills. "I don't know," he said. In order to optimize waste sites, it is planned to install sorting units in the village of Inderbor and Esbol rural district in the district. |
||||
|
Source of funding |
Plan, million tenge |
Fact, million tenge |
Reasons for not using |
|
||
|
1 |
2 |
3 |
4 |
|
||
|
Priority development of non-resource industries |
|
|||||
|
Other sources |
10 |
553,3 |
|
|
||
|
Total |
10 |
553,3 |
|
|
||
|
Improving the competitiveness of agribusiness sectors |
|
|||||
|
Other sources |
1,1 |
1,2 |
|
|
||
|
Total |
1,1 |
1,2 |
|
|
||
|
Ensuring employment and creating new jobs |
|
|
|
|||
|
Republican budget |
85,1 |
85,1 |
|
|
||
|
Local budget |
80,0 |
80,0 |
|
|
||
|
Total |
165,1 |
165,1 |
|
|
||
|
Ensuring the quality of services of general secondary education and pre-school education |
|
|||||
|
Local budget |
1145,8 |
233,2 |
|
|
||
|
Total |
1145,8 |
233,2 |
|
|
||
|
Increasing the availability of social infrastructure facilities for citizens |
|
|||||
|
Republican budget |
428 |
385,1 |
|
|
||
|
Local budget |
724 |
346,2 |
|
|
||
|
Total |
1152 |
731,3 |
|
|
||
|
Increasing the pace of housing construction to ensure housing affordability for citizens |
|
|||||
|
Republican budget |
4253,5 |
3033,3 |
|
|
||
|
Local budget |
999,7 |
618 |
|
|
||
|
Total |
5253,2 |
3651,3 |
|
|
||
|
Providing the population with high-quality drinking water, modernization of infrastructure facilities |
|
|||||
|
Local budget |
100 |
63,3 |
|
|
||
|
Total |
100 |
63,3 |
|
|
||
|
Improving the condition of local roads |
|
|||||
|
Local budget |
966,7 |
654,2 |
|
|
||
|
Total |
966,7 |
654,2 |
|
|
||
|
Total: |
8 793,9 |
6 052,9 |
|
|
||
Priority development of non-resource industries. According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars. According to the results of 2021, the volume of investments in fixed assets in the manufacturing industry, according to regional statistics, amounted to 553.3 million US dollars. In the reporting year «ГИПС ИНДЕР» LLP invested млн 235.8 million in the production of dry building mixes and building gypsum.investments in the amount of tenge are attracted.
Improving the competitiveness of agro-industrial sectors. In the reporting year, the volume of gross agricultural output amounted to 11 billion US dollars. 512 million.Tenge, the physical volume index is 104.1%.In 2020, 11 farms with a total area of 1,545 hectares were engaged in increasing the share of crop production, including drip irrigation, including 471 hectares by drip method. In 2021, 1,590 hectares were allocated for the entire crop, of which 779 hectares, i.e. 49%, were irrigated by drip method by 17 farms. For animal husbandry, it is planned to develop a fund to increase the area under forage crops to 490 hectares, and in the reporting year-to 500 hectares. In order to update the agricultural machinery fleet, 13 units of agricultural machinery and equipment (tractors and aggregates)were purchased in the reporting year. These are" Dastan " - 1," ER Tostik "- 1, farm"Asyl Agro "-2, individual entrepreneurs"Esmagambetov "-2,"Zhalgasbayev "-2,"Uteshov" -2, multi-specialty agricultural college Inder-1, LLP" Kaztatservis " - 1. in addition, 17 farms purchased drip irrigation equipment, 4 farms purchased sprinkler irrigation equipment.
Ensuring employment and creating new jobs. In 2021, it is planned to create 1,271 new jobs in the district. By the end of the year, 1,758 new jobs were created in the district (including 869 permanent and 889 temporary). "In particular, 45 people were created within the framework of the state programs" "employment roadmap for 2020-2021"", 99 places - within the framework of the housing construction program" "Nurly zher"", 805 places - within the framework of the program ""Enbek"", 22 places - under the program ""Auyl El besigi"", 581 places - at employers of the district, since the beginning of the year 206 new entrepreneurs have been registered in the tax department.
In the district, from January 1 to December 31, 2021, the number of recipients of social assistance (conditional monetary assistance) was 542 people, including 374 able-bodied people, the share of able-bodied people among recipients of targeted social assistance was 69.0%.
Ensuring the quality of services of general secondary education and pre-school education. According to the state program for the development of education in the Republic of Kazakhstan for 2021-2025, approved by the decree of the head of state, the quality of education is growing every year.
The secondary school named after K. Eskaliyev in the village of esbol was recognized as an emergency school based on the conclusion of "Techexpert-Eco" LLP No. 00266 dated February 12, 2017. Currently, construction of a school for 320 children is underway in Esbol village. The contractor is "Ondasyn Stroy" LLP.There is no three-shift school.
The number of children with disabilities enrolled in general education schools determined by the medical, pedagogical and psychological expert commission for health reasons in the district is 154. of these, 146 children with special educational needs are covered in 12 out of 15 schools. On April 23, 2021, the Regional Department of Education sent 2 Budget applications for the necessary equipment for creating inclusive conditions in schools. However, no funds were allocated.
Increasing the availability of social infrastructure facilities for citizens. In recent years, special attention has been paid to the development of Physical Culture and sports in the country. The main goal in this area is to promote the health of young people by leading a healthy lifestyle. Bukhara mass sports events were held jointly with akims and institutions of the district to promote sports among young people, show the importance and specifics of sports. In 2021, 373.7 million tenge was allocated from the Republican budget for the project "Auyl El besigi", the construction of a sports complex in the village of Zharsuat is being completed, and the construction of a sports complex in the village of Koktogay continues. 195 million tenge was allocated from the local budget for the purchase of the building of the Sports Complex in the village of Orlik and transferred to the balance sheet of the Department of Physical Culture and sports of Atyrau region. In 2021, 3 sports grounds were put into operation. These are a sports field in the KSU "secondary school named after sh.Ualikhanov" in the village of inderbor, a sports and playground located at the intersection of Taisogan and Kunayev streets in the village of inderbor, and a sports field in the KSU "secondary school named after S. Seifullin" in the village of inderbor.
Increase the pace of housing construction to ensure housing affordability for citizens. According to the results of 2020, the total housing stock was 669,735.5 sq. m., and in January –December 2021, 462 apartments with an additional area of 53,338 sq. m. were put into operation. The total housing stock in the reporting year was 723,073.5 sq. m.and 22.2 sq.m. per person.. (population-32545).
The number of multi – row residential buildings in the district is 64, of which the number of dilapidated housing is 19, or 29.6%. Due to the fact that the housing commissioned in the reporting year is planned to be transferred to the categories of large families and low-income families, it is not possible to move the housing recognized as dilapidated. No funds were allocated for the construction or purchase of housing in this category.
Providing the population with high-quality drinking water, modernization of infrastructure facilities. 13 settlements of the district are fully provided with clean water. For 2021-2022, 63,297.9 thousand tenge was allocated and fully disbursed at the expense of the regional budget for water treatment plants for autumn-winter work.
Improving the condition of local roads. The length of local roads is 219.9 km, including highways in good and satisfactory condition-169.7 km, the share of which is 77.2%. During the reporting year, 131.3 million US dollars were spent at the expense of the local budget to complete major repairs of intra-village access roads and pedestrian crossings in the settlements of Koktogay and Eltay.the funds were allocated and fully disbursed. Major repairs of 10.8 km of intra-village highways and pedestrian paths in Orlik village will be completed under the contract in December 2022.
Improving the environmental situation in the region. In January-December of this year, 6,684 tons of solid household waste were collected, 2,706 tons were removed to the landfill, and 570 tons or 21.1% were manually sorted.
The level of provision of social benefits and services to rural localities. The level of provision of social benefits and services in rural localities in accordance with the system of regional standards is 75.7%. In particular, in the settlements: Inderbor – 88.9%; Zharsuat, Quodene, Eltay, Esbol, Orlik and Koktogay – 84.2%; Yntymak and Akkala - 80 %; Aktan and Ketebay – 50%; Kyzylzhar -60%; Kurylys-70%.