Today about 144 localities of 474 were gasified it composes 30.4%.
Work is being completed on laying intra-block networks for the IV-th stage, in total, 17.5 thousand subscribers out of 54.3 thousand were connected.
Construction of intra-village networks of settlements in the Balkhash, Karatal, Koksu, Kerbulak and Eskeldy districts has begun.
"In total, 6.2 billion tenge was allocated for gasification in Almaty region this year, including 4.8 billion tenge from the budget.