Akim of the district T. Bayedilov inspected the work on major repairs of the drinking water system in the village of Buleksaz. In general, the work will begin in 2020 and will be fully completed by December 2021. The contractor made several comments to the head of Daneker LLP and demanded that the shortcomings be corrected as soon as possible. To date, 7.6 km of drinking water has been supplied to the village and has been fully completed. The mayor of the district explained to the population of the village about the connection of drinking water to each house and made comments. By the end of the year, full supply of drinking water will be provided.