Reconstruction of the water supply system of Nura village is carried out

Reconstruction of the water supply system of Nura village is carried out

According to the electronic contract of public procurement for the reconstruction and construction
of the water supply system of the village of Nura, work began on June 9, 2022. The total length of the project is 17.9 km. The works are planned for 2022-2023. Currently, 48 units of wells (well) have been installed, 13 pieces of wells (well) have been prepared, 40 sets of wells (well) have been installed, 186 PM trenches. Work continues. The customer is the State Institution "Department of Housing and Communal Services, Passenger Transport, highways and Housing Inspection of the Enbekshikazakh district".
Author's supervision: ElM LLP; Technical supervision: Kobylan Expert LLP; Contractor organization: SMU VOSTOK LLC, SMU Vostok LLC.