In Almaty, a heating main almost 6000 m long has been completely replaced

In Almaty, a heating main almost 6000 m long has been completely replaced

In the Zhetysu district in the microdistrict. In Ainabulak, the reconstruction of heating networks, begun by order of Almaty Heating Networks LLP two years ago, has been completed. The total length of heat supply networks is 5865 m.

In 2022, 1730 m were reconstructed, in 2023 – 2000 m and in 2024 – 2135 m.

This year, reconstruction was completed on the section of the TM-18 “Ainabulak” heating main on the street. Makataev (from Zhumabaev St. to Pavlodarskaya St.).

The main construction and installation work was completed before the onset of the autumn-winter period of 2024-2025.

Currently, the site is being improved - paving the road surface with a fine-grained layer, after which road markings will be applied.

It should be noted that the heating main was put into operation in 1981, its service life was 43 years, while the standard service life is 25 years.

The project will provide high-quality heat supply to residents of 344 apartment buildings, 11 schools, 3 healthcare facilities and 483 other facilities.

This year, on behalf of Almaty Akim Erbolat Dosayev, 20 km of heating networks were reconstructed; work was carried out in 6 districts of the city during the inter-heating period. Landscaping of areas after reconstruction is carried out in stages depending on weather conditions.