B. Sagintayev checked the pace of infrastructure development in New Almaty

B. Sagintayev checked the pace of infrastructure development in New Almaty
During a working detour, akim of the megapolis Bakhytzhan Sagintayev got acquainted with the construction of water supply and sewerage networks, roads and social facilities in the attached micro-districts.
 
In md. Algabas, Alatau district, the first stage of construction of 17 km of water supply networks and 13.5 km of water disposal is nearing completion. 1,332 subscribers will be connected to them. At the second stage, the construction of 19.1 km of water supply networks and 13.7 km of water disposal, as well as 14 km of pressure sewerage networks, continues. About 1.5 thousand subscribers will be connected. Also for the full provision of residents of the microdistrict. Algabas with centralized water supply and sewerage is developing design estimates for the III stage of construction.
 
As the engineering work is completed in the microdistrict. Algabas will restore 11.3 km of roads on 24 streets. To date, 3.9 km of 10 streets have been restored. In addition, 31.9 km of new roads will be built on 98 streets. To date, asphalt concrete pavement has been laid on 9 streets with a length of 4.2 km. Other streets will be temporarily covered.
 
Outdoor lighting has been installed on 21st street. Akim of the city instructed to speed up the installation of outdoor lighting on the remaining two streets. In addition, 73.5 km of electrical networks will be modernized with the replacement of 32 transformer substations.
 
Thus, the living conditions in the md. Algabas, home to 21,000 people, will be improved to meet citywide standards. This concerns the quality of the services supplied and the tariffs for electricity and water supply, which have so far been supplied by private organizations.
 
The same work is being done in the Nauryzbay district. So, in microdistrict Akzhar continues construction of 19 km of water supply networks and 15.7 km of water disposal.
 
 According to the project, 1400 houses will be connected to them. Completion of the project is scheduled for next year. It is planned to modernize 5.5 km of networks and replace 3 transformer substations. In 2020, outdoor lighting lines were laid along 49 streets as part of the current renovation.
 
Akim of Almaty B. Sagintayev also got acquainted with the progress of road construction in the microdistrict Tastybulak. Today, asphalt concrete pavement has been laid on 17 streets with a length of 10.1 km. The asphalting of one 1.1 km long street will be completed shortly. Also, the akim of the city examined the progress of the improvement of the embankment of the Tastybulak river.
 
In order to develop transport links in the north-western part of the city, a large-scale project is underway to punch st. Saina from Ryskulov ave. To st. Monke B. The total length is 3.2 km. To date, work is being carried out on a section of 1.4 km. Preparation of the base, embankment and reinforcement of slopes has been completed. B. Sagintayev instructed to accelerate the pace and increase the volume of work. The six-lane road will increase the mobility of residents of the Alatau district and residents of suburban settlements in the Almaty region.
 
Work continues to provide affordable housing. B. Sagintayev examined the first 4 built houses for 144 apartments in the residential complex "Madeniet". Asphalting of the territory and installation of street lighting is in progress. In total, it is planned to build 22 houses with 792 apartments. So, 211 apartments will be distributed among socially vulnerable groups of the population, 24 - among working youth, 557 - among those on the waiting list and depositors of Otbasy Bank.
 
By order of the akim of Almaty B. Sagintayev, the construction of a kindergarten and three schools is envisaged in the development of a detailed plan. Thus, residents will be provided with social services within their neighborhood.
 
In md. Kalkaman continues construction of a new building of GKB # 7. The attendance of the emergency room will be up to 650 people per day. There are 48 beds for patients. Akim of the city got acquainted with the progress of construction work and the list of equipment. It is planned to purchase CT machines, X-rays, ventilators, mobile X-ray systems, medical monitors and multifunctional beds.
 
 B. Sagintayev instructed to speed up the finishing and construction and installation work in order to quickly put the new medical institution into operation. The main goal is to improve the quality of medical services provided to the population.