57 thousand sq. m of roadbeds repaired in Almaty

57 thousand sq. m of roadbeds repaired in Almaty
In the megapolis, the current repair of roads continues, about 3 thousand potholes have been removed on 460 streets.
 
 
Since the beginning of April, with the onset of favorable weather conditions, 2936 defects have been eliminated - pits, potholes, subsidence on 459 streets. Including 96 main lines, 363 - of regional significance. The total area of ​​the repaired track is 56,729 sq. In the course of the work carried out, 656 hatches and gratings were raised, and 1370 linear meters of curb stones were straightened.
In total, it is planned to renovate more than 250 thousand square meters. m of asphalt concrete pavement, 40 stopping pockets and platforms.
 
More than 400 workers and 155 units of special equipment are involved in daily repairs.
 
Roadworks plan for April 27:
 
Alatau district:
1. TR Kuderin - Ryskulov.
2. Monke Bi St.
 
Zhetysu district:
1. Microdistrict Ainabulak.
2. Yesim Khan St.
3. Kazybaeva St.
 
Auezov district:
1. Sadovnikov St.
2. Pyatnitsky St.
3. 2nd microdistrict.
4. Shchepkin St.
 
Nauryzbay district:
1. Akbat St.
2. Sagdiev St.
3. Elibaeva St.
4. Smayilova St.
 
Almalinsky district:
1. Duisenov St.
2. Karyernaya St.
 
Medeu district:
1. Ualikhanov St.
2. Tulebaeva St.
3. Igisheva St.
 
Turksib district:
1. Baimagambetov St.
2. Microdistrict Zhas Kanat.
3. Aytykov St.
 
Bostandyk district:
1. Kozhakeeva St.
2. Mustafina St.
3. Biocombinatskaya St.
4. Microdistrict Koktem.
 

We ask residents of the city to adjust their route in advance.