As the head of the Energy and Utilities Department of the city Yermek Usenbayev reported, the repair of the heating networks is in the final stage and will be completed as planned before the start of the heating season.
So, on the reconstructed site of .Tole bi st. along the Sayran reservoir and the sections of Masanchi and Kazybek bi streets, the completion of works with the arrangement of the roadway is scheduled for October 10.
On the sections of Baishev and Tobayakov streets the full completion of the technical part is planned by October 12.
Since September 20, traffic has opened on the reconstructed bridge along Abai Avenue through the Esentay River. Overhaul of the bridge, built in 1964 and in an emergency condition, allowed to expand the roadway to six lanes. The installation of a new bridge, the concreting of the main river bed, the reorganization of networks, the installation of a barrier and perimeter fencing. Water-filled safety buffers are installed on both sides of the separation fence, designed to mitigate the impact in the event of an accident. To date, work is under way on the construction of a pedestrian crossing under a bridge construction and improvement of the adjacent territory.
Recall that in the current year were allocated funds for the construction and repair of 32 km of sidewalks and 182 km of roads, construction of 14.7 km and reconstruction of 42.2 km of irrigation networks in 57 streets, the construction and reconstruction of 317 km of urban water supply networks and 265 km of sewerage , 32 km of heating networks. Commissioning of 284 km of new water supply networks will make it possible to connect 35,000 residential houses to the centralized water supply, where more than 175,000 people live.