Appendix 2
IMPLEMENTATION OF THE ACTION PLAN
on the implementation of the suggestions and comments of the population raised during the preparation and holding of the reporting meetings Akim of Mugalzhar district in 2021
as of _1 April 2021
|
№ |
Name of the question |
State of execution |
Stage of execution |
|
Mugalzhar district |
|||
|
1. |
Construction of a sports and recreation complex (FOC) in Kandyagash |
In 2020, funds in the amount of 50.0 million tenge were allocated from the regional budget in the "Mugalzhar district in Kandyagash for the construction of a sports and recreation complex". According to the results of the competition, the winner was recognized as the PC "Erzat". The total cost of the project is 402.5 million tenge. The remaining funds were allocated from the republican budget. The customer of the object of the State Institution "Department of Construction of the Aktobe region" in 2021. it is planned to hand over the object for full use. To date, the site has been excavated, as well as works on the construction of the base of the building and the creation of metal structures. |
On performance |
|
2. |
Installing a traffic light in front of secondary school No. 4 in Kandyagash |
In April 2018, the relevant project document was developed and reviewed through the Office of the Mayor of the city of Kandyagash. The total cost is 5.6 million tenge. An open competition was announced, and today the results of the preliminary admission are being summed up. |
On performance |
|
3. |
Repair of Tlepbergenova str., Emba |
For 2021, funds were allocated in the amount of 230.3 million tenge (RB-207.3 million tenge, OB-23 million tenge). The Public Procurement Department of the Aktobe region has announced a competition, the winner will be determined on 12.04.2021. The competition is at the appeal stage. |
On performance |
|
4. |
Solving the problems of drinking water in Taldysay village |
For 2021, funds were allocated in the amount of 283.3 million tenge (RB-226.6 million tenge, OB – 56.6 million tenge).) The winner of the competition is Monolit LLP. Contractual work is underway with the contractor. |
On performance |
|
5. |
Solving the problem of drinking water in the village of Zharyk |
For 2021, funds were allocated in the amount of 447.6 million tenge (RB-358.1 million tenge, OB-89.1 million tenge), the Department of Public Procurement of the Aktobe region announced a competition, the winner of the competition – Daneker LLP. Contractual work is underway with the contractor. |
On performance |
|
6. |
Solving the problem of drinking water in the village of Bashili |
For 2021, funds were allocated in the amount of 427.8 million tenge (RB-342.2 million tenge. OB-85.5 million tenge.) The winner of the competition is Monolit LLP. Contractual work is underway with the contractor. |
On performance |
|
7. |
Solving the issue of major repairs of the Shengelshi village school |
In 2021, 51.7 million tenge was allocated from the budget (RB-46.5 RUB - 5.2), funds were allocated and a competition was announced. 7 contractors took part in the competition, and the documents are currently being checked. It is expected that the results of the competition will be summed up on 02.04.2021. |
On performance |
|
8. |
Provision of apartments to residents of Emba. |
In 2020, funds were allocated for the multi-storey building No. 11 (45-apartment) on B. Momyshuly Street-about 100.0 million tenge, and in 2021 125.3 million tenge, work is underway. The contractor is PC Erzat. In 2021, funds from the budget of 432.5 million tenge were allocated for the multi-storey building No. 15 (90-apartment). The competition is at the appeal stage, it will be announced on 08.04.2021. Department of Public Procurement of the Aktobe region. |
On performance |
Akim Mugalzhar district А.Sheryazdanov
@ G.Askarov
(:8(71333)3-14-04